Brigham and Women’s Faulkner Hospital received approval for the Determination of Need (DoN) submission in May 2022 to begin working on a campus expansion program to better support care in our communities. Construction began in May of 2023.
We welcome your feedback! Contact us at cdelaney5@mgb.org.
Construction Update: May 12-23, 2025
Garage
- Garage demolition continues over the next two weeks.
- A second excavator will be delivered to the site on Monday, May 12 at 7:00 a.m.
- Landscaping work to be completed by Friday, May 16.
Inpatient Addition
Work Within Hospital Spaces
- 2nd Floor
- Continued use of Hospital Loading Dock.
Exterior Site Work
- Main Entry island curbing and paving expected to be completed by Monday, May 12.
- Cross walk striping expected to be completed on Monday, May 12 and Tuesday, May 13.
- Main Entry lane closure expected to reopen on Tuesday, May 13.
- Main Entry island landscaping expected to be completed by May 16.
Interior Work Within Inpatient Addition
- 1st floor: Final clean and punch list.