Please note, the majority of BWFH’s campus expansion construction work is now complete. Updates will be provided monthly or as needed.
Current Construction Updates: July 2025
Garage
- The old garage structure has been demolished and removed from the site. The current effort is associated with the installation of underground utility / drainage systems and site grading.
- Rear garage (new) PV array – The PV array system is undergoing regulatory / legal reviews and there are no updates to the installation schedule at this time.
Inpatient Addition
- Work Within Hospital Spaces: Internal punch list activities will continue through the remainder of the year.
- Grounds: Exterior plantings, fencing and irrigation will continue through the fall.
We welcome your feedback! Contact us at cdelaney5@mgb.org.