Campus Expansion

at Brigham and Women's Faulkner Hospital

BWFH's Campus Expansion

Brigham and Women’s Faulkner Hospital received approval for the Determination of Need (DoN) submission in May 2022 to begin working on a campus expansion program to better support care in our communities. Construction began in May of 2023.

We welcome your feedback! Contact us at cdelaney5@mgb.org.


Construction Update: May 26 - June 6, 2025

Garage

  • Demolish remaining parts of the existing garage structure with crane support for protection.
  • Remove demolished garage concrete and steel from site.
  • Begin removal of existing retaining walls and footings. Removal may require hammering which will cause some additional noise.
  • Install new vinyl graphics at new Hillside Garage elevators.
  • Complete landscaping (weather dependent).

Inpatient Addition

Work Within Hospital Spaces

  • 2nd Floor
    • Continued use of Hospital Loading Dock.
    • Saturday 5/31:
      • Patch and repair CMU walls at level 2 loading dock.
      • Shut down Cafeteria RTU D to install economizer.

Exterior Site Work

  • Saturday 5/31: Repair and replace telephone/data manhole cover at Hillside Garage Main Entrance.
  • Punchlist landscaping, hardscaping, and irrigation completion.

New Inpatient Building

  • Relocate Endoscopy 4 Medical Gas panel.
  • Install patient room bathroom grab bars.
  • Miscellaneous “day 2” work.