Brigham and Women’s Faulkner Hospital received approval for the Determination of Need (DoN) submission in May 2022 to begin working on a campus expansion program to better support care in our communities. Construction began in May of 2023.
We welcome your feedback! Contact us at cdelaney5@mgb.org.
Construction Update: May 26 - June 6, 2025
Garage
- Demolish remaining parts of the existing garage structure with crane support for protection.
- Remove demolished garage concrete and steel from site.
- Begin removal of existing retaining walls and footings. Removal may require hammering which will cause some additional noise.
- Install new vinyl graphics at new Hillside Garage elevators.
- Complete landscaping (weather dependent).
Inpatient Addition
Work Within Hospital Spaces
- 2nd Floor
- Continued use of Hospital Loading Dock.
- Saturday 5/31:
- Patch and repair CMU walls at level 2 loading dock.
- Shut down Cafeteria RTU D to install economizer.
Exterior Site Work
- Saturday 5/31: Repair and replace telephone/data manhole cover at Hillside Garage Main Entrance.
- Punchlist landscaping, hardscaping, and irrigation completion.
New Inpatient Building
- Relocate Endoscopy 4 Medical Gas panel.
- Install patient room bathroom grab bars.
- Miscellaneous “day 2” work.