Brigham and Women’s Faulkner Hospital received approval for the Determination of Need (DoN) submission in May 2022 to begin working on a campus expansion program to better support care in our communities. Construction began in May of 2023.
We welcome your feedback! Contact us at cdelaney5@mgb.org.
Current Construction Updates: June 2025
Garage
- Continue sort, separate, and remove demolition debris.
- Begin removal of existing retaining walls and footings. Removal may require hammering which will cause some additional noise.
Inpatient Addition
Work Within Hospital Spaces
- 2nd Floor
- Continued use of Hospital Loading Dock.
New Inpatient Building
- Level 1: Medication room reconfiguration, level 1 area alarm panel installation, and MRI room millwork completion.
- Level 2: Relocation of Endo 4 Zone Valve Box, medication room sink relocation.
- Level 3-5: Caulking at patient room sliders, miscellaneous punch list and OFCO install, Biomed wiring to telemetry monitors.
- Miscellaneous “day 2” work.